Escalonamento de projetos com restrições de recursos e múltiplos modos de processamento: soluções heurísticas e uma aplicação à programação de manutenção industrial
Data
Autores
Título da Revista
ISSN da Revista
Título de Volume
Editor
Universidade Federal do Espírito Santo
Resumo
This master's thesis presents an implementation of the GRASP meta-heuristic for solving the Multi-mode Resource constrained Problem of Scheduling Project (MRCPSP). The MRCPSP belongs to the class NP-Hard and therefore has received attention of many researchers. In this thesis, a case study problem of Scheduling Industrial Maintenance is viewed as a MRCPSP. The GRASP was tested with a set of benchmark tests obtained from PSPLIB (Project Scheduling Library). The results showed that the GRASP is a good strategy for solving MRCPSP instances.
Descrição
Palavras-chave
Project scheduling, Industrial maintenance, Metaheuristic, Combinatorial optimization, GRASP, MRCPSP, Escalonamento de projeto, Manutenção industrial, Meta-heurística
Citação
CRAVO, Gildásio Lecchi. Escalonamento de projetos com restrições de recursos e múltiplos modos de Processamento: soluções heurísticas e uma aplicação à programação de manutenção industrial. 2009. Dissertação (Mestrado em Informática) - Universidade Federal do Espírito Santo, Centro Tecnológico, Vitória, 2009.